Claims Support and Evidence Record.
Build the claim while the job runs.
Are we recovering what we are owed? ARK checks your site record for gaps every day, opens a dated evidence file on every change, and tests each claim against the contract before you send it.

Every record kept. Every change filed. Every claim tested before it goes.
Records kept
ARK Watcher flags missing daily reports, photos and T&M tickets while your people can still remember the day.
Changes filed
A dated timeline of the evidence starts the moment a drawing, an RFI answer or a meeting direction changes the job.
Claims tested
Every notice rule is checked as Pass, Fail or Arguable, the evidence rated for each cost, and the letter drafted for you.
1
Construction claimsWhat is construction claims support, and what does ARK do with it?
Construction claims support is keeping the records that prove a change, giving the right notice on time, and testing the claim against the contract before it goes. ARK checks your daily reports, photos and T&M tickets for gaps, opens a dated evidence file every time a drawing, RFI answer or meeting direction changes the job, and tests each claim against the contract’s notice rules before you send it. It works on claims against you too.
2
What it costs youWhat a thin record costs you
You are owed more time or money when something outside your control changes the job. To get paid you must give the right notice on time and prove what happened with records made at the time.
That is where most claims fail: on notice, or on thin records. Rarely on the merits. The same applies in reverse when a claim or a deduction comes at you.
3
What ARK does, step by stepHow ARK supports a claim
Checks the record daily
Every working day, ARK Watcher tests daily reports, photos and T&M tickets against your standard and sends the gaps to your Superintendent the same day.
Opens a file on every change
A revised drawing, a scope-changing RFI answer or a meeting direction starts a dated timeline of the evidence, plus what is still missing.
Captures what was said
After every meeting, pulls out decisions, directions and commitments with who said them and when, and flags anything left out of the minutes.
Tests the claim
Checks each notice rule as Pass, Fail or Arguable, rates the evidence for each cost and drafts the letter. Works on claims against you too.
Your team decides: Your Project Manager and Contracts Manager approve and send. ARK never sends anything.
4
See it on a live projectAsk ARK, and get the source with the answer.
Ask ARK
“Certificate 15 deducts 14 days of liquidated damages. Did we meet every notice requirement?”
ARK returns
Notice Arguable. Formal claim 35 days after the revised drawing, against a 28-day limit. 10 working days supported by the schedule update, 142,300 of direct cost evidenced against a 168,000 deduction, one unsigned ticket flagged as weak, letter drafted for review.
5
Ask yourselfWhen the owner’s representative knocked back your last extension of time, was it on the merits, or on the notice?
6
What ARK reads, and who it is forWhat ARK reads
- Daily reports, photos and T&M tickets, in your project management platform or site apps.
- RFIs, drawings and transmittals, in your CDE.
- Meeting minutes and transcripts, in your meeting and collaboration tools.
- Schedule baseline and updates, pay applications and certificates.
- The contract and your documentation standard.
Who it’s for
Project ManagerA claim tested against the notice rules before it goes, with the letter drafted.
Contracts ManagerEvery notice rule as Pass, Fail or Arguable, with the clause cited.
Commercial ManagerThe evidence rated for each cost, and the weak items flagged.
SuperintendentThe gaps in today’s record, sent today, while the day is still fresh.
7
What feeds it and what it feedsWhere this sits in the project
- 1TenderBid Packages and Trade Scopes
- 2PreconstructionEstimating and Cost Intelligence
- 3Contract AwardContract De-Risking Before Signature
- 4ConstructionSubmittal Reviews and RFI Watch · Quality Before Cover-Up
- 5Commercial ControlClaims Support and Evidence Record · Closing the Cost Loop
- 6Handover and Close-outCommissioning Readiness and Handover Data
Contract De-Risking Before Signature sets the notice rules, Submittal Reviews and RFI Watch feeds the answers that add scope, and The Foundation feeds the drawing revisions. The event files explain the margin moves in Closing the Cost Loop and on the Protect your margin page. Back to What ARK Does
8
FAQ